Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : DEOGARH (NEAR DHANDHANIYA)-RAJASTHAN/GUJARAT BORDER (PHASE-I) (AJ/DRGB-PACKAGE-6).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    20

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
846.590846.59

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
106.5948.526.23161.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20234/20254/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
83.970

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Ongoing

Monthly Status

Background Information

Project total length is 25.00km & cumulative physical progress achieved till March month is 98.00%.Project total length is 25.00km & cumulative physical progress achieved till March month is 89.15%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone