Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : DEOGARH (NEAR DHANDHANIYA)-RAJASTHAN/GUJARAT BORDER (PHASE-I) (AJ/DRGB-PACKAGE-6).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
846.590846.59

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
161.345.91.67167.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20237/20257/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
83.970

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.25Ongoing

Monthly Status

Background Information

Project total length is 25.00km & cumulative physical progress achieved till June month is 99.25%.Project total length is 25.00km & cumulative physical progress achieved till March month is 89.15%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks