Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4 LANING OF CHAMPA-KORBA-CHHURI-KATGHORA SECTION OF NH 149B FROM KM.0.000 TO KM.38.200.

Reported Date : 01-MAY-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    8

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
999.970999.97

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
948.5800948.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20240/09/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
124.450

Ministry Review Date

LatestLastPhysical Progress (%)Status
89.7Completed

Monthly Status

Background Information

Project is under construction stage. 33.50km is completed out of 38.20km.Project is under construction stage.33.35km is completed out of 38.20km.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone