Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4 LANING OF PATHRAPALI TO KATGHORA FROM KM.53.300 TO KM.92.600.

Reported Date : 03-OCT-23

Monthly Report : 9 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
865.10865.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
641.7813.9.2655.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20223/20233/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
71.510

Ministry Review Date

LatestLastPhysical Progress (%)Status
92.48Completed

Monthly Status

Background Information

PCOD issued by IE for part length i.e. 31.08km w.e.f. 16.06.2023

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks