Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4 LANE OF BILASPUR TO URGA PROJECT (KM 0.00 TO KM 70.2) OF NH-130A.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   36.01

Time Overrun (Months)-    18

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1855.592523.862523.86

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
368.32224.60592.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/09/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
179.94312.74

Ministry Review Date

LatestLastPhysical Progress (%)Status
88.94Ongoing