Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : AMRITSAR AIRPORT JUNCTION RAMDAS FROM KM. 100.835 TO KM. 139.813 PKG IV.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
524.88416.58416.58

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
157.1400157.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20239/20259/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1200

Ministry Review Date

LatestLastPhysical Progress (%)Status
73Ongoing

Monthly Status

Background Information

Construction work is in progressConstruction work is in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks