Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : BANGALORE/TN BORDER TO HOSKOTE.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1240.61181.681181.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
927.7915.139.95952.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20259/20259/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
88.12325.2

Ministry Review Date

LatestLastPhysical Progress (%)Status
83.25Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks