Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF SANNUR TO BIKARNAKATTE SECTION FROM KARKALA TO MANGALORE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   28.26

Time Overrun (Months)-    14

Total/Pending/Completed Milestone - 4 / 2 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1409.681808.121808.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
675.29278.5216.11969.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/202412/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
192.270

Ministry Review Date

LatestLastPhysical Progress (%)Status
55.35Ongoing

Monthly Status

Background Information

The physical progress achieved so far is 50.35%. Out of 45.012 Km only 27.1 km is completed. Anticipated date of completion is 31/12/2025.The physical progress achieved so far is 38.04%. Out of 45.012 Km only 19.26 km is completed. Anticipated date of completion is 08/10/2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land4/20234/2025PendingImmediatePending at MoEFCC,IRO Bangalore

Ongoing Milestone

Completed Milestone