Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF SANNUR TO BIKARNAKATTE SECTION FROM KARKALA TO MANGALORE.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1409.681808.121808.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
969.9262.526.731039.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20246/20266/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
192.270

Ministry Review Date

LatestLastPhysical Progress (%)Status
59Ongoing

Monthly Status

Background Information

The physical progress achieved so far is 59%. Out of 45.012 Km only 27.5 km is completed. Anticipated date of completion is 30/06/2026.The physical progress achieved so far is 38.04%. Out of 45.012 Km only 19.26 km is completed. Anticipated date of completion is 08/10/2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land4/20239/2025PendingImmediatePending with User Agency due to EDS raised by DCF Kundapur