Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : TUMKUR - NELAMANGALA(6L).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2032.152032.152032.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
177.487.38.78185.64

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20253/20263/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
236.02236.02

Ministry Review Date

LatestLastPhysical Progress (%)Status
52.88Ongoing

Monthly Status

Background Information

Cumulative length completed till June 2025 is 10.3 km. Target for the month of June is 1 Km and length completed is 0 km. therefore there is shortfall of 1 km.Target for the month of March 24 was 1km and achievement is 0.32 km. However, Cumulative Target for the FY has been achieved therefore there is no shortfall in achievement.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks