Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : AURAD - BIDAR KM 0.00 TO KM 45.878.

Reported Date : 25-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    20

Total/Pending/Completed Milestone - 4 / 4 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
912.370424.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
326.360-70.42255.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/202312/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

AS on date, 45.72 Kms of Length has been completed. The Cumulative Physical Progress as on date is 99%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone