Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF CHANNARAYAPATNA BYPASS AND HASSAN BYPASS WITH STRUCTURES IN DEVIHALLI -HASSAN SECTION.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    28

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
688602.09688

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
462.1139.6312.49514.23

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20239/20205/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
76.620

Ministry Review Date

LatestLastPhysical Progress (%)Status
80.02Ongoing

Monthly Status

Background Information

Physical progress was achieved by EPC Contractor is 80.02% Out of 39.13 Kms only 30.92 Kms work has been completed. Now Anticipated date of completion is 31 May 2025 Physical progress was achieved by EPC Contractor is 74.17%.Out of 39.13 Kms only 26.77Kms work has been completed. Now Anticipated date of completion is 31 March

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone