Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4 LANING OF BAHADURGANJ ARARIA SECTION FROM KM 49.000 TO KM 94.000 (PACKAGE-II) OF NH-327E.

Reported Date : 27-NOV-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 11 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1143.461143.461143.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
425.19126.160551.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/202412/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.69Completed

Monthly Status

Background Information

Physical Progress = 82.70% Financial Progress = 75.01% Out of 45.00 km, 40.55 km work has been completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone