Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 2ND FLYOVER (LCW) PARALLEL TO EXISTING FLYOVER IN KISHANGANJ TOWN..

Reported Date : 06-SEP-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 8 / 2023

Cost Overrun (%)-   1.26

Time Overrun (Months)-    38

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
150.21152.1152.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
148.402.58150.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20208/20238/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Physical Progress = 100% Financial Progress = 100% Out of 3.18 km, 3.18 km work has been completed. PCC has been issue on dated 18.08.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone