Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANING OF MAMALLAPURAM TO MUGAIYUR SECTION OF NH332A FROM KM 0.000 TO KM 31.000.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1008.991360.531360.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
303.4821.330324.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20248/20253/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2500

Ministry Review Date

LatestLastPhysical Progress (%)Status
18-MAR-2550.33Ongoing

Monthly Status

Background Information

Four laning work is in progressFour laning work is in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks