Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : KARAIPETTAI TO WALAJAPET FROM KM 71.015 TO 107.091.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   8.28

Time Overrun (Months)-    51

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
707.9766.51766.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
401.9885.5338.88526.39

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20210/05/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
173.98173.98

Ministry Review Date

LatestLastPhysical Progress (%)Status
88.25Ongoing

Monthly Status

Background Information

"Length completed 33.25 km out of 36.076 Km as on 31.03.2025 Physical progress- 88.25% as on 31.03.2025""Length completed 25.66 km out of 36.076 Km as on 31.03.2024 Physical progress- 70.82% as on 31.03.2024"

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone