Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 6L OF SRIPERUMBUDUR TO KARAIPETTAI FROM KM 37.000 TO KM 71.015 OF NH 48.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   12.56

Time Overrun (Months)-    44

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
819.891314.82922.85

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
361.9832.7720.85415.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20210/01/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
193.23193.23

Ministry Review Date

LatestLastPhysical Progress (%)Status
57.32Ongoing

Monthly Status

Background Information

Out of 34.015 km, 17.195 Km has been completed at Physical progress of 57.32%. Due to non-supply of Pond Ash by Thermal Power Plants at free of cost to site as per MoEF &CC circular dated 25.1.2016, the work of approaches to the structures is delayed. Due to which the contractor has been foreclosed. The contractor completed 17.195 Km and the balance work has been awarded to the new contractor & the appointed date is declared on 27.01.2025 & the works are in progress."Length completed 17.21 km out of 34.015 Km as on 31.03.2024 Physical progress- 54.83% as on 31.03.2024"

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone