Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 12.56
|
Time Overrun (Months)-
44
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Out of 34.015 km, 17.195 Km has been completed at Physical progress of 57.32%. Due to non-supply of Pond Ash by Thermal Power Plants at free of cost to site as per MoEF &CC circular dated 25.1.2016, the work of approaches to the structures is delayed. Due to which the contractor has been foreclosed. The contractor completed 17.195 Km and the balance work has been awarded to the new contractor & the appointed date is declared on 27.01.2025 & the works are in progress. | "Length completed 17.21 km out of 34.015 Km as on 31.03.2024
Physical progress- 54.83% as on 31.03.2024"
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |