Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L FROM GAJU VILLAGE AT KM 32.982 TO DEVINAGAR BYPASS (END) AT KM 208.000 OF NH 530B (PKG 1C).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1384.7901384.79

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
657.9400657.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20250/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
319.850

Ministry Review Date

LatestLastPhysical Progress (%)Status
97.98Ongoing

Monthly Status

Background Information

The cumulative physical progress at the end of the month was accounted to 72.87%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks