Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF HARDA - BETUL (PKG-II) FROM KM. 30.00 TO KM.81.00 [TEMAGAON TO CHICHOLI].

Reported Date : 27-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
520.280520.28

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
274.43118.42.01392.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20252/20252/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
182.4144.83

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone