Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : INDORE - HARDA (PKG-I) [INDORE TO RAGHAV GARH FROM KM. 0.25 TO KM. 26.903].

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1011.2901011.29

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
245.1339.6733.96318.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20240/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
99.060

Ministry Review Date

LatestLastPhysical Progress (%)Status
70.68Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks