Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : DEVELOPMENT OF 4L UER II [PACKAGE - V] (SPUR TO BAHADURGARH BYPASS) (NH-10) FROM KM. 0.00 TO KM.7.30.

Reported Date : 03-MAR-25

Monthly Report : 2 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
801.460801.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
382.03091.73473.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20230/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
431.760

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.33Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks