Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SANCHORE - SANTALPUR FROM KM 67.000- KM 99.000 OF NH-754K (AJ-RGBS-PACKAGE-3).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   1.85

Time Overrun (Months)-    16

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
752.30766.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
451.1101.02452.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/202312/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
536.820

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.14Ongoing

Monthly Status

Background Information

As per settlement agreement signed on 10.05.2024 & likely completion date =10.04.2025

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone