Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SANCHORE - SANTALPUR FROM KM 4.888 - KM 35.000 OF NH-754K (AJ-RGBS-PACKAGE-1).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   8.32

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
606.510657

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
453.8900453.89

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20233/20245/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
525.010

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.99Ongoing

Monthly Status

Background Information

CC was issued on 12.12.2023 as per the settlement agreement signed on 09.04.2024. The project is already completed.Under Construction Physical Progress - 98.98% Financial Progress - 98.29 %

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone