Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : BALANCE WORKS OF 4L AMRAVATI - CHIKHLI (PKG I) [AMRAVATI TO KURANKHED FROM KM. 166.00 TO KM. 220.00].

Reported Date : 05-JAN-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    3

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
713.070713.07

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
02810281

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20230/010/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
56.560

Ministry Review Date

LatestLastPhysical Progress (%)Status
78.5Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone