Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF END OF PINJORE BYPASS - BADDI - NALAGARH SECTION (KM. 4.200 TO KM. 35.370) OF NH21A.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1692.0501692.05

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
942.1400942.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20240/09/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
77.920

Ministry Review Date

LatestLastPhysical Progress (%)Status
21.6Ongoing