Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd..
Project Name : PEREN-DIMAPUR PKG-3.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 4 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
177.77199.02199.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
43.333.61046.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
32.060

Ministry Review Date

LatestLastPhysical Progress (%)Status
63.33Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks