Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : 4 LANE FROM KM 56.400 TO KM 120.300 FROM B.KOTHAPALLI JUNCTION TO GORANTLA OF NH 716G.

Reported Date : 09-JUN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
839.980839.98

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
146.1200146.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20250/09/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
67Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone