Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : INDORE - EDLABAD (PKG-II) [TEJAJINAGAR TO BALWARA].

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1162.801162.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
373.31105.896.38485.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20250/01/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
319.180

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone