Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : IMPROVEMENT OF GEOMETRICS OF THONDUPALLY TO KOTHUR FROM KM 22.300 TO KM 34.14 OF NH-44-RCW.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
541.580541.58

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
27.777.12.0934.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20240/01/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
311.08311.08

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Construction work is going on

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks