Project Summary
Project Summary
Sector Name : SHIPPING AND PORTS.
Agency Name : PORT TRUST.
Project Name : DEEPENING OF CHANNEL AT PARADIP PORT.

Reported Date : 08-JAN-15

Monthly Report : 11 / 2014

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
154.84253.36253.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
221.58026.31247.89

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
52.020

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks