Project Summary
Project Summary
Sector Name : SHIPPING AND PORTS.
Agency Name : SHIPPING CRP. OF INDIA.
Project Name : ACQUISITION OF 6 NOS. OF 57000 DWT HANDYMAX BULK CARRIERS.

Reported Date : 11-JUN-12

Monthly Report : 4 / 2012

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1061.961077.61082.06

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1143.890140.261284.15

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/04/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1403.430

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks