Project Summary
Project Summary
Sector Name : SHIPPING AND PORTS.
Agency Name : PORT TRUST.
Project Name : CONSTRUCTION OF CAPTIVE JETTY FOR HANDLING COAL, NPCL, KARNATAKA.

Reported Date : 01-MAR-12

Monthly Report : 12 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2300230

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
21900219

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20100/06/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks