Project Summary
Project Summary
Sector Name : SHIPPING AND PORTS.
Agency Name : SHIPPING CRP. OF INDIA.
Project Name : ACQUISITION OF TWO NOS. OF 120 B.P BY 079AND 080.

Reported Date : 11-APR-13

Monthly Report : 2 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
290.85272.5272.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
86.46107.68100.38294.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20110/02/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
101.81172.63

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks