Project Summary
Project Summary
Sector Name : SHIPPING AND PORTS.
Agency Name : SHIPPING CRP. OF INDIA.
Project Name : ACQUISTION OF THREE(3) NOS OF 6500TEU CELLULAR CONTAINER VESSELS FROM M/S STX SHIPBUILDING CO. LTD..

Reported Date : 30-JAN-15

Monthly Report : 11 / 2014

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1028.11012.231012.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
371.96182.640554.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/201311/201311/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks