Sector Name : SHIPPING AND PORTS.
Agency Name : SHIPPING CRP. OF INDIA.
Project Name : ACQUISITION OF ONE (1) NOS. OF 3500 TEU CELLULAR CONTAINER.

Reported Date : 30-JAN-15

Monthly Report : 11 / 2014

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
220.490220.49

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
47.320047.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20136/201311/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed