Project Summary
Project Summary
Sector Name : SHIPPING AND PORTS.
Agency Name : KAMARAJAR PORT LIMITED.
Project Name : CONSTRUCTION OF COAL BERTH-3 AT KAMARAJAR PORT LIMITED.

Reported Date : 05-JUL-18

Monthly Report : 4 / 2018

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
198.94247255

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
255.0200255.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/201711/20170/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2042.75

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

KPL completed the berth construction on 15.11.2017. Top side facilities to be erected by TANGEDCO for commissioning of berth.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks