Project Summary
Project Summary
Sector Name : SHIPPING AND PORTS.
Agency Name : Inland Waterways Authority of India.
Project Name : JAL MARG VIKAS PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 7 / 3 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5369.185061.155061.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3426.88014.673441.55

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202312/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
994.330

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-MAY-2568.86Ongoing

Monthly Status

Background Information

Progress achieved (1) Varanasi MMT: Completed (Terminal inaugurated by the Prime Minister on 12.11.2018) (2) Sahibganj MMT: Completed (Terminal dedicated to the Nation by the Prime Minister on 12.09.2019) (3) Haldia MMT: Terminal is inaugurated by Hon’ble Prime Minister on 13.01.2023. (4) New Navigational lock at Farakka: Inaugurated by Hon’ble Prime Minister on 17.10.2023 (5) KalughatIMT: Inaugurated by Hon’ble Minister of Shipping on 15.02.2024 and five-star GRIHA ratings achieved. Progress achieved during the month month (1) Varanasi MMT: Completed (Terminal inaugurated by the Prime Minister on 12.11.2018) (2) Sahibganj MMT: Completed (Terminal dedicated to the Nation by the Prime Minister on 12.09.2019) (3) Haldia MMT: Terminal is inaugurated by Hon’ble Prime Minister on 13.01.2023. (4) New Navigational lock at Farakka: Inaugurated by Hon’ble Prime Minister on 17.10.2023 (5) KalughatIMT:0.4% Inaugurated by Hon’ble Minister of Shipping on 15.02.2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone