Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : MAHANAGAR TELEPHONE NIGAM LIMITED.
Project Name : EXP. OF 750K GSM LINES OF 2.5 GSM AND VALIDATION EQUPT. WCDMA.

Reported Date : 24-NOV-10

Monthly Report : 9 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
741.770278.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
151.3700151.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20070/09/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks