Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : GSM EQUIPMENT-480K LINES(2G) AND 220K LINES(3G) IN UP(W)-PH-V.I.

Reported Date : 27-MAR-12

Monthly Report : 1 / 2012

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
335.910335.91

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
169.4313.020182.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20090/03/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
99.30

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks