Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : MAHANAGAR TELEPHONE NIGAM LIMITED.
Project Name : EXPANSION OF EXISTING 2GAND3G GSM N/W BY 750 KPE NO 9920/05-06.

Reported Date : 24-NOV-10

Monthly Report : 9 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
180.530180.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
25.970025.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20090/09/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks