Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : PROCUREMENT OF DXC EQUIPMENT.

Reported Date : 02-MAR-12

Monthly Report : 12 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2290229

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0000

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20100/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks