Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : MAHANAGAR TELEPHONE NIGAM LIMITED.
Project Name : EXPN OF EXISTING 2G AND 3G GSM N/W BY 750K.

Reported Date : 30-DEC-10

Monthly Report : 10 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
180.530180.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
40.920040.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20100/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project is in commercial use with full capacity.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks