Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : GSM EQUIPMENT OF 1700000LINES (2G) 234100 LINES 3(G)KARNATAKA PHASE V.1 TELECOM CIRCLE.

Reported Date : 02-MAR-12

Monthly Report : 12 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
677.75719.9719.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
395.0666.50461.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20090/03/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3250

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks