Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : GSM/UMTS IN KARNATAKA LOT 1 (2G+3G).

Reported Date : 06-DEC-16

Monthly Report : 10 / 2016

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
154.120154.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
56.1523.624.9884.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20160/010/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
97.970

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

It is a GSM /UMTS in Karnataka circle LOT-1 Phase VII+. Capacity 6.16 Lakh lines (2G+3G BTS 2048). 2048 (2G+3G) BTS achieved and 100% physical progress completed. Hence The project may be treated as completed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks