Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : MAHARASHTRA NODAL (LOT 1).

Reported Date : 07-FEB-19

Monthly Report : 12 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
159.3159.3159.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
060.27060.27

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/201812/201812/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
125125

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

It is a Phase VIII.4 Nodal LOT1 GSM project. Network elements planned 12 and installed till Dec-18 12. As per Circle/Business Unit report for the month Dec-18 the project has completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks