Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : MAHARASHTRA CORE (LOT1).

Reported Date : 08-MAR-19

Monthly Report : 1 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
167.680167.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
032.44032.44

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20181/20191/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
122.93122.93

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

It is a GSM Phase VIII.4 Core LOT1 project. Network elements planned 128 and installed till jan-19 128 As per circle/Business unit report the project is completed in the month of jan-19.As the project has been completed by 31.01.2019 i.e before the anticipated date as informed earlier i.e 28.02.2019 furnished in the month dec-18.accordingly the time over run has been reduced as per original date of commissioning.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks