Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : UP (EAST) ACCESS LOT1.

Reported Date : 06-DEC-18

Monthly Report : 10 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
169.450169.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
078.34078.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/201810/201810/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
124.84124.84

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Its a GSM Phase VIII.4 Access LOT 1 project. Capacity 16.8 Lakh Lines. BTS planned 2065 and installed 2065 till date The UP (East) circle has completed the PH VIII.4 Access GSM Project.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks