Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : MAHARASTRA METRO RAIL CORPORATION LTD..
Project Name : FARIDABAD EXTENSION.

Reported Date : 09-DEC-15

Monthly Report : 10 / 2015

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
249402494

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1164.03133.813.71311.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20140/08/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
137.210

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition0/00/0PendingImmediateAt few locations, though notifications has been issued but compensation to owners has not been paid by HUDA.