Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CENTRAL PUBLIC WORKS DEPARTMENT.
Project Name : STAGE I OF PHASE C/O PERMANENT CAMPUS FOR IIM.

Reported Date : 09-APR-19

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 2 / 2019

Cost Overrun (%)-   4.98

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
332.720349.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
305.1815.95.97322.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20160/09/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

All the construction works are completed under this sanction.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone