Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CENTRAL PUBLIC WORKS DEPARTMENT.
Project Name : ACADEMIC CUM RESIDENTIAL CAMPUS AT HARINGHANTA KALYANI WB FOR IISER KOLKATA.

Reported Date : 05-JUL-16

MOU Status : Project Under MOU for 2015-2016

Monthly Report : 5 / 2016

Cost Overrun (%)-   0

Time Overrun (Months)-    47

Total/Pending/Completed Milestone - 16 / 1 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
225.810225.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
143.7200143.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20123/20165/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1010

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone