Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CENTRAL PUBLIC WORKS DEPARTMENT.
Project Name : RESIDENTIAL AND OTHER COMPLEXES FOR THE CAMPUS OF IIT PATNA AT BIHTA.

Reported Date : 24-JUN-16

Monthly Report : 5 / 2016

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
171.1200200

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
191.99.250192.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20147/20157/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
184.5200

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks