Project Summary
Project Summary
Sector Name : DEPARTMENT OF HIGHER EDUCATION.
Agency Name : CPWD OF HIGHER EDUCATION.
Project Name : DIFFERENT BUILDINGS UNDER PHASE 1 NORTH FOR IIT MANDI AT KAMAND.

Reported Date : 08-JUL-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
270.830244

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
235.3200235.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20140/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone